Description 
    The existing accesses (concrete stairs and escalators) to the platforms in Antwerp South station will be demolished and replaced by a bicycle lift and precast concrete stairs.
We are also building a new bridge with on-site poured abutments, piers and lift shafts topped by precast concrete girders. Once completed, the annexed bridge will serve as a covered bicycle shed.
A special feature of the project is the train environment, which will involve a lot of phasing and weekend work
location 
    Project Details
                        Contractor                    
                    
                Kolonel Silvertopstraat, Antwerpen, Antwerpen, Belgium
                     
                    Client 
    NMBS
      Architects 
    NMBS
      Engineering Office 
    NMBS
      Construction period
2 years 7 months
Start work
11-2022
End of work
06-2025
 
                    






 
                                       